Checking sewing capacity before accepting an order

A practical example of checking an RMG order against available sewing minutes.

Start with the order quantity and the standard minute value (SMV). For example, 5,000 pieces at 12 minutes per piece require 60,000 sewing minutes.

Reserve time for washing, finishing and shipment after sewing. Compare the required minutes with available line capacity before the resulting sewing end date. Subtract confirmed bookings before deciding which line can take the order.